GE (NYSE: GE) presented a comprehensive roadmap to support the 2010 Ministry of Energy and Water's plan for the development of Lebanon's power sector from the point of generation, to transmission, distribution and consumption at a seminar themed 'Powering Lebanon Forward'. The event was held under the patronage of the Ministry of Energy and Water and attended by over 140 participants, including H.E. Cesar Abi Khalil, Lebanon's Minister of Energy and Water, H.E. Elizabeth H. Richard, United States Ambassador to Lebanon, government officials, industry experts, power plant owners and operators, engineering, procurement and construction (EPC) contractors, developers, consultants and others.
H.E. Cesar Abi Khalil, Lebanon's Minister of Energy and Water, said, "Our foremost commitment is to build the electricity infrastructure of the country to meet the shortage of power, which is important to drive infrastructure development and all-round progress. We can transform the country's power ecosystem with the active participation of private sector corporations such as GE, whose comprehensive roadmap and technologies meet our requirements to develop the strong fundamentals needed for a sustainable energy future for our country."
According to estimates, Lebanon has an energy shortfall of 1.5 gigawatts (GW). Moreover, the demand for power is projected to continue growing at an estimated 5 percent annually from 2018 to 2021, and at 3 percent beyond 2021 through to the end of 2030. The challenge of generation shortages is further compounded by grid-related issues such as dilapidated networks and unauthorized connections.
The roadmap has proposed to:
Add up to 1.5 GW through fast power technology and new simple cycle power plants that are tri-fuel capable - able to run on heavy fuel oil (HFO), light diesel oil (LDO) and natural gas, as well as wind power plants that can help to generate clean energy, in the short-term.
Increase power generation capacity by up to an additional 1.3 GW through new combined cycle power plants, the conversion of simple cycle power plants to combined cycle power plants so that more power can be generated from the same amount of fuel, and new wind power farms, in the medium-term.
Bring online up to another 2.7 GW to meet the country's energy needs through new combined cycle power plants and renewable energy facilities, in the long-term.
Strengthen the grid through extensions to up to 6 existing substations and developing up to 17 new substations.
Install an Integrated Energy Management system to allow the Ministry to identify losses in the network.
"GE has been present in Lebanon since the early development of its energy sector, with the first GE steam turbine in the country commissioned in 1987 and the first GE gas turbines entering operations in 1996. Today, we are excited to build upon this legacy of contributions with a comprehensive roadmap for the electrification of Lebanon that can help strengthen the country's power sector for present and future generations and build the foundations needed to enable progress for the people," said Midhat Mirabi, General Manager of GE's Power Services business in the East Mediterranean, North Africa and Iraq sub-region.
GE operates across more than 20 countries in the Middle East, North Africa and Turkey (MENAT) and has supported the development of the region's power sector for more than 80 years. Today, more than 2,450 GE gas and steam turbines are installed by over 360 customers in MENAT and can generate up to a third of the region's power. The company also has offices in Beirut with over 90 direct and indirect employees.
Beiruting News
Other news
-
What's up ?A Taste of Home, A Legacy Since 1820: Faouzi Hawasli 1820 Opens in Beirut
26 november 2026 -
What's up ?Milord Opens Its New Flagship Boutique in Naccache
26 november 2026 -
What's up ?Toura marks Lebanon’s 83rd Independence Day with a concert at Haret Kanaan in Jezzine JEZZINE
23 november 2026 -
What's up ?14 MORE WISHES, 14 MORE DREAMS: TAWFEER AND TAMANNA JOIN FORCES AGAIN TO BRING HOPE TO CHILDREN ACROSS LEBANON
22 november 2026 -
What's up ?Philip Morris Lebanon organizes community environmental clean-up initiative in Bikfaya
20 november 2026 -
What's up ?NISSAN OFFICIALLY LAUNCHES THE ALL-NEW TEKTON IN THE MIDDLE EAST WITH BOOKINGS NOW OPEN
19 november 2026 -
What's up ?AndMore Ventures Unveils Its Christmas 2026 Season: Three Experiences That Bring Lebanon Together
12 november 2026 -
What's up ?L'Oréal-UNESCO For Women in Science Honours Six Exceptional Arab Researchers at the 13th Levant Ceremony
12 november 2026 -
What's up ?Two Lebanese Designers Named Finalists in Regional ‘Creators of Craft’ Design Challenge, led by Vogue Arabia in Collaboration With IQOS, With the Participation of Italian Design House Seletti
09 november 2026 -
What's up ?Batroun Capitale de Noel
09 november 2026 -
What's up ?Miss Lebanon Perla Harb Heads to Puerto Rico for Miss Universe 2026
09 november 2026 -
What's up ?Beirut Chants brings audiences together through music in its 19th edition
06 november 2026 -
What's up ?Artists & More Entertainment Partners with The Revive Club and Wael Arakji to Empower Sports and Inspire Lebanon’s Young Generation
04 november 2026 -
What's up ?A Lebanese Dream, A Global Vision: Sara Safa’s Journey Beyond Borders
04 november 2026 -
What's up ?Georges Khabbaz Honored at the Opening of the 20th Beirut Shorts International Film Festival
01 november 2026 -
What's up ?ZUHAIR MURAD x ALDO
01 november 2026 -
What's up ?Lebanese Designer Jad Soda Joins IQOS and OUCHHH Collective to Unveil CURIOUS STUDIO at Dubai Design Week 2026
26 october 2026 -
What's up ?Lebanese Canadian University (LCU) Celebrates Over 25 Years of Achievements
21 october 2026 -
What's up ?From Kitchen Appliances to Toys: The Rise of One-Stop Online Shopping in Lebanon
16 october 2026 -
What's up ?Healthy Days Fair Takes Achrafieh by Storm
12 october 2026